Pow-Sys Power Systems logoPow-Sys Power Systems
Request a QuoteTürkçe

MV Project Approval and Medium Voltage Design

For facilities that need an approved medium voltage project — a new connection, transformer capacity increase, MV switchgear renewal or SPP/generator integration — EMO-registered engineers prepare the MV project file and support the EDAŞ / OIZ / TEDAŞ approval process. Deliverables include the single-line diagram, MV switchgear arrangement, short-circuit and voltage-drop calculations and authority revision tracking, so approval delays and design gaps become visible before they block your investment. To receive a proposal, simply share your energy permit or connection conditions, installed power, transformer capacity and existing single-line diagram.

Engineering-FocusedField ExperienceStandards ComplianceEnergy EfficiencyFast Proposal24/7 SupportCertified TeamMeasurement & ReportingData-Driven Improvement
MV switchgear, transformer substation and single-line diagram study within the scope of medium voltage installations design
Medium voltage installations design covers site survey, energy permit, single-line diagram, MV switchgear arrangement, technical calculations and authority approval process.

Last updated: July 9, 2026

Reviewed by Hüseyin ÇOKAL, Electrical and Electronics Engineer. Updated: July 9, 2026.

What changed: Service scope, report outputs, official sources, pre-proposal information and technical transparency notes were reviewed for the current period.

MV Project Approval and Medium Voltage Design Summary

  • Medium voltage installations design services for industrial facilities, OIZ factories, power generation plants and large commercial buildings: one engineering team from energy permit to acceptance
  • Site survey, energy demand analysis, single-line diagram and project file preparation within the scope of MV installation design: a file built on real facility data, not templates
  • Energy permit, connection opinion, EDAŞ / OIZ / TEDAŞ project approval process and authority revision tracking: authority requirements followed so revisions do not stall the investment
  • MV switchgear, transformer substation, cable route, grounding, surge arrester and protection system evaluations: safety-critical selections documented before installation
  • Short-circuit calculation, voltage drop, cable sizing, load analysis and relay coordination studies: equipment sized by calculation, not assumption
  • Technical support during implementation control, testing, commissioning, provisional acceptance and final acceptance processes: the approved project verified on site before energization

Technically reviewed by

MV Project Approval and Medium Voltage Design Scope

What are MV project approval and medium voltage design?

Medium voltage installations design service covers the technical design of medium voltage electrical infrastructure above 1 kV and up to 36 kV in practice for industrial facilities, OIZ factories, power generation plants, large commercial buildings and infrastructure projects, in compliance with official authority processes and with engineering control during the implementation stage. As Pow-Sys Power Systems, we provide medium voltage installations engineering, MV installation design and MV project approval process support across Türkiye. For related context, see Electrical Installation Conformity Report and Periodic Inspection.

A medium voltage project is not merely a drawing preparation process. The facility’s energy demand, installed power, demand power, transformer capacity, MV switchgear structure, cable route, protection system, grounding arrangement, energy permit and official authority requirements must be evaluated together. For this reason, technical calculations, site conditions and authority approval requirements are handled as a whole during the MV installation design process. For related context, see Electrical Contracting Services.

Required Documents for a Medium Voltage Project

The documents required for a medium voltage project may vary depending on the requirements of the connected distribution utility, OIZ, TEDAŞ or relevant authority. A typical file includes the energy permit, connection opinion, facility information, load list, installed power data, transformer capacity, single-line diagram, MV switchgear arrangement, cable route, technical calculations and application forms. For related context, see Electrical Periodic Inspection and Examination Service.

Site survey, energy demand and existing condition assessment

Before starting project studies, a site survey and existing condition analysis are carried out. Transformer substation, MV switchgear, low-voltage panels, cable connections, compensation system, grounding installation, metering circuits and previous project documents, if available, are reviewed. This study helps determine the correct project scope for a new facility installation, capacity increase, transformer capacity change or existing MV installation revision. For related context, see Short-Circuit Analysis, Relay Coordination and Selectivity.

One of the first steps in the design process of medium voltage installations is determining the energy demand correctly. Installed power, demand power, simultaneity, production lines, motor loads, generator connection, solar power plant connection, backup supply requirement and critical loads are evaluated together. These data form the main inputs for selecting transformer capacity, MV switchgear structure, cable sizes and protection system.

What are an energy permit and connection opinion?

Energy permit and connection opinion are important stages in the MV project process. The technical requirements determined by the relevant distribution company, OIZ directorate or authority directly affect the project. Therefore, when preparing a medium voltage project, the power, connection point, voltage level, supply method and authority requirements stated in the energy permit must be carefully reviewed.

Single-line diagram, MV switchgear layout and project documents

Within the scope of MV installation design, single-line diagram, load list, MV switchgear arrangement, transformer substation layout, cable route, panel layouts, grounding plan, cable sizing calculations, short-circuit calculations, voltage drop calculations and implementation projects can be prepared. When required, different project documents such as preliminary design, final design, implementation project, revision project and as-built project can also be created.

MV switchgear arrangement is one of the most critical topics in the medium voltage installations design process. Incoming cubicle, metering cubicle, transformer protection cubicle, outgoing cubicles, coupling cubicle and spare cubicle requirements should be planned according to the facility’s operating scenario. During switchgear arrangement, maintenance access, cable entry-exit directions, switching safety, operator use and official authority expectations are considered.

Transformer substation, cable route and equipment selection

In MV installations with transformer substations, transformer capacity, transformer type, cooling structure, installation area, ventilation, fire safety, cable connection directions, maintenance access, transportation possibility and safety clearances must be evaluated together. During transformer substation design, not only the initial investment cost but also long-term operational safety and maintenance convenience are taken into account.

Short-circuit, voltage drop, grounding and protection coordination

Short-circuit calculation is one of the fundamental parts of medium voltage installations engineering studies. Short-circuit levels are required for correct selection of MV switchgear, circuit breakers, disconnectors, busbars, cables, transformers and protection equipment. Equipment selected without calculation may fail to provide adequate safety during a fault and may put operational continuity at risk.

Voltage drop and cable sizing calculations are important for the healthy operation of loads supplied from MV installations. Cable lengths, load currents, route conditions, installation method, ambient temperature and voltage level are evaluated together to determine the appropriate cable size. This study is necessary for both energy efficiency and facility safety.

Grounding and surge arrester systems must also be carefully handled during the MV installation design process. The grounding system is critical for safely transferring fault currents to earth, ensuring life safety and protecting equipment. Surge arrester selection and lightning protection approach become especially important in open field, transformer substation and overhead line connection applications.

Protection coordination and relay selectivity studies ensure that the system responds correctly during faults in MV installations. The aim is to clear the fault only at the relevant point, keep healthy sections energized and prevent unnecessary trips. In this scope, short-circuit results, transformer data, circuit breaker characteristics, protection relay curves and operating scenarios are evaluated together.

When required, load-flow analysis, arc-flash risk assessment, harmonic effects, compensation behavior and power quality topics can also be evaluated during the medium voltage project process. These reviews help ensure that MV switchgear, transformers, cables, busbars and protection equipment are selected according to real operating conditions.

How does the MV project approval process proceed?

The MV project approval process is not completed only by preparing the drawings. The project file must be prepared according to the relevant authority requirements, technical calculations must be added to the file, application documents must be arranged, authority revisions must be tracked and the post-approval implementation process must be carried out in accordance with the project. Approval authority belongs to the relevant institutions; Pow-Sys Power Systems provides technical file preparation, revision tracking and engineering support.

Differences between EDAŞ, OIZ and TEDAŞ project approval

EDAŞ, OIZ, TEDAŞ and EMO processes play an important role in medium voltage installations design studies. During project approval, application file, technical revision, official acceptance file, provisional acceptance, final acceptance and report processes, the documents must be consistent with the actual site condition. Facilities without an approved project or with site implementation that does not comply with the approved project may face problems during the acceptance stage.

When is a medium voltage project required

Medium voltage installations design service may be required in many cases such as new facility investments, transformer substation installation, transformer capacity increase, MV switchgear renewal, overhead line connection, solar power plant connection, generator integration, panel revision, capacity increase, power quality problems or official authority approval processes.

Are MV project approval and acceptance the same process?

MV project approval is the authority review and technical approval process for the prepared medium voltage project file. Acceptance is the field process that checks whether the on-site implementation complies with the approved project, authority requirements and technical safety conditions. Therefore, project approval and acceptance complement each other, but they are not the same process.

Implementation control, testing and commissioning

Correct transfer of the project to the site is also important during implementation. MV switchgear layout, cable route, cable terminations, transformer connections, grounding connections, panel connections, labeling, metering circuits and protection equipment should be checked on site. Conditions that do not comply with the project or may create operational risks in the future can be reported in writing.

During testing and commissioning, the necessary checks are carried out to energize the MV installation safely. MV switchgear, circuit breaker, disconnector, protection relay, transformer, grounding, continuity, metering circuits, compensation and other systems deemed necessary are tested and inspected. These studies also provide the technical basis for provisional acceptance and final acceptance processes.

Quotation process and Pow-Sys approach

During the quotation process, facility type, installed power, demand power, transformer capacity, number of MV switchgear units, existing single-line diagram, energy permit status, EDAŞ / OIZ / TEDAŞ process, cable distances, transformer substation condition, capacity increase information, site survey requirement and commissioning scope are evaluated together. This allows us to prepare a phased engineering proposal that reflects the real technical scope of the MV project process, rather than only a general price.

Pow-Sys Power Systems approaches medium voltage installations design not only as a project drawing service, but as an engineering study that considers energy continuity, operational safety, authority approval process, technical calculations, implementation control and long-term facility needs together.

For medium voltage installations design, MV installation design, medium voltage installations engineering, MV project drawing, MV project approval process, short-circuit calculation, protection coordination or EDAŞ / OIZ / TEDAŞ authority tracking, you can share your facility information and request a project-specific comprehensive engineering evaluation. Scope is clarified from this information, and before signing you see in writing what is included and what is planned as a separate service.

Reporting, Inspection and Proposal Preparation

Sample Inspection Table

This table summarizes which headings are evaluated on site and which outputs may appear in the report.

Inspected areaChecked criterionReport output
Site and equipment conditionExisting equipment structure, access conditions, visible risks and operating conditionsSite inspection note and prioritized findings list
Document and project conformitySingle-line diagram, current project, labeling, reports and conformity with site implementationDocument conformity assessment and missing record list
Safety and operational riskLife safety, equipment safety, energy continuity and maintenance access risk headingsRisk classification and corrective action recommendations
Measurement, test or inspection needMeasurement, test, visual inspection and technical review items required by the service scopeMeasurement/test plan or inspection scope note
Reporting and follow-upNonconformity priority, follow-up date, responsibility allocation and next stepsPhoto-supported report, action list and follow-up recommendation

MV Project Approval Process - 7 Steps

Pow-Sys handles the MV project approval process not merely as drawing preparation, but as an engineering workflow that combines utility requirements, field survey, technical calculation, revision tracking and commissioning support.

StageInputPow-Sys output
Preliminary meeting and document checkFacility type, installed power, transformer data, existing single-line diagram, old project and utility correspondenceScope note, missing document list and initial technical risk headings
Energy permit / connection opinion checkConnection opinion, power, voltage level, connection point and utility requirementsUtility requirement assessment and application requirements list
Field surveyExisting single-line diagram, MV switchgear, transformer, cable route, panel and grounding conditionField observation note, project-site conformity check and photographed finding list
Single-line diagram and technical calculationsLoad list, cable distance, transformer power, switchgear data and protection arrangementShort-circuit, voltage drop, cable cross-section, grounding and relay coordination outputs
Utility applicationProject file, application documents, authorization scope and utility file formatApplication-ready technical file and revision tracking list
Revision trackingTechnical revisions, missing document and clarification requests received from the utilityRevision tracking table, updated project note and response preparation
Post-approval implementation / commissioning supportApproved project, site condition, implementation items and pre-commissioning check headingsDeficiency/nonconformity list, pre-commissioning check note and follow-up recommendation

Pow-Sys MV Project / Approval Anonymous Field Data Set

The table below summarizes the recurring headings encountered in medium voltage project/approval work and the typical Pow-Sys engineering output, without sharing any real customer or facility name.

Reviewed facility typeFrequent findingTypical riskPow-Sys action
Production facility with a private transformer inside an OIZThe existing single-line diagram does not fully match the site.Utility revision, incorrect connection or commissioning delay risk arises.A single-line revision list, MV switchgear check note and pre-commissioning follow-up item are prepared.
Energy generation / solar plant (GES) connected facilityThe energy permit, connection opinion and project scope are not clearly separated in the same file.Additional information requests may arise during the application and revision process.A utility requirement check note, technical calculation list and revision tracking table are created.
Hospital, shopping mall or large commercial buildingCritical loads, backup supply and pre-commissioning testing need are not clear.Energy continuity and operational safety decisions may remain incomplete.A critical load note, pre-commissioning checklist and separate testing need are reported.

Pow-Sys Field Observations and Anonymous Finding Headings

Without sharing real facility or company names, technical findings frequently encountered during field work are summarized below. No quantity or ratio is given where a real numerical record is not maintained.

Observation headingTypical site riskPow-Sys action
Outdated project or single-line recordA mismatch between site equipment and documents may increase the risk of wrong decisions, missing maintenance or incorrect switching.Revision need is stated in writing and document follow-up is recommended according to the current field condition.
Labeling and equipment identification gapsUnclear panel, switchgear, cable or equipment names may create confusion for field personnel.Labeling, equipment identification and instruction updates are added to the action list.
Scattered maintenance, test or measurement recordsUntraceable historical records may cause recurring faults, delayed maintenance and audit preparation problems.Report history, follow-up date and records to be completed are written as separate items.
Need for measurement or separate testingGrounding, thermal imaging, relay testing or insulation testing may require separate planning outside the main service.Separately planned test/measurement headings and priority level are added to the report.

Anonymous MV Project and Approval Case Examples

The following examples show the field experience, technical assessment and delivery output in the MV project approval process, without sharing any customer name, facility name, address, serial number or commercial capacity.

Anonymous case - private transformer facility inside an OIZ

Date
May 2026
Facility type
Production facility with a private transformer inside an OIZ; Bursa region; 34.5 kV connection; 2x1600 kVA transformer range
Anonymous tracking code
og-proje-onay-vaka-2026-01
Previous condition
The energy permit, existing single-line diagram, switchgear arrangement and site implementation were not tracked under the same revision order.
Finding
The scope was broken down into energy permit, single-line diagram, short-circuit calculation, cable cross-section, relay coordination and pre-commissioning project-site conformity check.
Action
For the project-site mismatch and missing revision tracking, a project revision list, MV switchgear check note and pre-commissioning check output were prepared.
Measurable output
5 technical calculation headings, 1 utility requirement note, 1 revision tracking table and 4 switchgear check notes were created.
Follow-up result
The revision items were transferred to the technical file review before the utility application.
Limit / note
The customer name and facility address were not shared due to KVKK/confidentiality; the final project decision depends on a current field survey and the relevant utility's assessment.

Anonymous case - energy generation connected facility

Date
April 2026
Facility type
Facility with an energy generation connection; Marmara region; 34.5 kV connection; single transformer substation and MV switchgear structure
Anonymous tracking code
og-proje-onay-vaka-2026-02
Previous condition
The energy permit, connection opinion and technical calculation scope were tracked in different files.
Finding
The scope was classified into connection opinion check, single-line diagram, short-circuit calculation, voltage drop, cable cross-section and protection coordination.
Action
Technical calculation outputs, a utility requirement check note and a revision tracking table were prepared.
Measurable output
5 technical calculation headings, 1 utility requirement note, 1 revision tracking template and 1 pre-commissioning check item were organized into the file structure.
Follow-up result
The missing documents and calculation headings before the application were shared with the customer.
Limit / note
The customer name and facility address were not shared due to KVKK/confidentiality; in generation facility connection processes, the final approval authority belongs to the relevant institution/organization.

Anonymous case - critical commercial building

Date
March 2026
Facility type
Large commercial building in the hospital/shopping mall segment; region outside Bursa; 34.5 kV supply; critical load and backup supply need
Anonymous tracking code
og-proje-onay-vaka-2026-03
Previous condition
Which panels fed the critical loads and the pre-commissioning testing need were not clear enough in the project file.
Finding
The scope was divided into load list, single-line diagram, generator integration, short-circuit result, relay coordination and pre-commissioning check headings.
Action
A critical load note, pre-commissioning checklist and separate test/measurement recommendation were prepared.
Measurable output
3 critical load notes, 2 separate testing needs, 1 utility requirement check note and 1 pre-commissioning check output were reported.
Follow-up result
The open headings were added to the technical meeting agenda before implementation.
Limit / note
The customer name and facility address were not shared due to KVKK/confidentiality; in buildings with high outage sensitivity, site implementation and commissioning inspection must be planned separately.

Out-of-Scope and Separately Planned Works

MV Project Approval and Medium Voltage Design produces technical follow-up, reporting, compliance assessment and risk notification. The following works are planned separately when required; final risk level, cost and scope are not confirmed without an on-site survey.

Out-of-scope / separate workWhy is it evaluated separately?Pow-Sys approach
Grounding measurementIt may require measurement equipment, site time and a separate report.The need is stated in the main report; measurement work is planned separately.
Relay testing and selectivityRelay settings, test equipment, outage planning and separate engineering assessment may be required.Quoted as a separate testing/selectivity service when needed.
Thermal imaging inspectionIt requires imaging under load and a separate thermal finding report.Planned separately for panels, switchgear or connections where risk is observed.
Transformer maintenance and oil analysisIt may require maintenance crew, sampling, laboratory work or a separate test procedure.The need is written in the technical report; maintenance/testing is prepared as a separate scope.
Project revision, implementation and physical remediationIt creates material, labor, authority process or implementation responsibility.The main service reports the finding; implementation and contracting works are handled separately.
Technical file and authority revision studies within the scope of MV installation design and MV project approval process
MV installation design includes technical file preparation, project revision, acceptance and commissioning support for EDAŞ, OIZ, TEDAŞ and EMO processes.
Anonymous technical report, checklist and follow-up output example
Standard report/control output: field finding, risk level, corrective action and follow-up date shown together.

Official Regulatory Sources

Frequently Asked Questions

What is MV project approval?

MV project approval is the authority review process for a medium voltage electrical project file. It brings together the energy permit, connection opinion, single-line diagram, MV switchgear arrangement, technical calculations and authority requirements for evaluation by the relevant distribution utility, OIZ, TEDAŞ or authorized institution.

What is medium voltage installations design?

Medium voltage installations design is the preparation of medium voltage electrical infrastructure above 1 kV and up to 36 kV in practice, considering the facility’s energy demand, voltage level, load characteristics, transformer substation, MV switchgear, cable route, technical calculations and authority approval process.

What does MV installation design include?

MV installation design may include site survey, energy demand analysis, single-line diagram, MV switchgear arrangement, transformer substation layout, cable route, short-circuit calculation, voltage drop, grounding, protection coordination, project file and authority revision tracking.

How is a medium voltage project prepared?

A medium voltage project is prepared by considering the energy permit or connection conditions, installed power, demand power, transformer capacity, MV switchgear structure, cable distances, technical calculations and official authority requirements.

When is a medium voltage project required?

A medium voltage project may be required for a new transformer substation, transformer capacity increase, MV switchgear renewal, capacity expansion, overhead line connection, solar power plant connection, generator integration, factory expansion or any electrical infrastructure change that requires official authority approval.

How does the MV project approval process proceed?

In the MV project approval process, the project file is prepared, technical calculations and required documents are added to the file, and an application is submitted to the relevant EDAŞ, OIZ, TEDAŞ or authorized institution. Revisions requested by the authority are tracked, and technical support is provided for the post-approval implementation and acceptance process.

Can an MV project be prepared without an energy permit?

In general, the energy permit, connection opinion or technical conditions determined by the authority are important in the MV project process. Since the project scope, connection point, power and voltage level are clarified according to these documents, these requirements should be evaluated before the project.

Do you provide support in EDAŞ, OIZ and TEDAŞ processes?

Yes. We provide technical support for project file preparation, technical revision tracking, application process, pre-acceptance checks, official acceptance file and commissioning stages. Approval authority belongs to the relevant institutions.

Get an MV Project Proposal

Let us bring your project to life together.

Contact us now for a site survey and preliminary discussion.

Contact Us
Call NowGet a Proposal